Research / Infrastructure

AI compute deals. When will the power arrive?

Who is buying capacity, who is building it, and when it is expected. Agreements and projects across AI labs, cloud providers, and neoclouds.

Dataset updated Sep 14, 2026 · Latest announcement Sep 8, 2026

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases7.75 GW10.5 GW300 MW
IT power leases1.77 GW200 MW
Campus projects1.9 GW

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

$428.1B

Stated contract values, over their full terms

Additional upper-limit values

Up to $45.4B

Additional minimum values

Over $400B

11 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 14 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Palantir10 of 1
Mistral AI21 of 2
CoreWeave43 of 4
Undisclosed buyer33 of 3
Crusoe10 of 1
Nscale31 of 3
Anthropic65 GW6 GW300 MW3 of 6
Microsoft64 of 6
Meta31 of 3
OpenAI72.75 GW4.5 GW0 of 7
NVIDIA10 of 1
Fluidstack11 of 1
xAI10 of 1
Cohere10 of 1

Time to Power

When is capacity expected?

17 dated targets · 23 without a first-capacity window

Assess a site →

3 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

Applied Digital / CoreWeave · 175 MW ready for service

Polaris Forge 1 campus; part of 400 MW contracted. Report date, not energization date.

Company update · 2026-07-27

2025

Original target passed

Microsoft / Nebius

Vineland, New Jersey, US · Late 2025 (announced target)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2025

Delivery reported

CoreWeave / Applied Digital

Ellendale, North Dakota, US · First 100 MW targeted for Q4 2025

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Original target passed

Anthropic / SpaceX

Site not disclosed · May 2026 (original target; later May–June ramp disclosed)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Original target passed

Fluidstack / TeraWulf

Lake Mariner, New York, US · First approximately 40 MW targeted for first half of 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–4 months away

Anthropic / CoreWeave

Site not disclosed · Later in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–4 months away

Nscale / Verne

Iceland · Deployment planned in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Undisclosed buyer / Applied Digital

Boyce, Louisiana, US · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Undisclosed buyer / Applied Digital

United States; state not identified in cited release · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Microsoft / Nscale

Narvik, Norway · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Anthropic / Google / Broadcom

Primarily United States · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Microsoft / Crusoe

Abilene, Texas, US · First building: mid-2027

First power · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Meta / Nebius

Multiple locations · not named · Early 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Microsoft / Nscale

Mason County, West Virginia, US · Late 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Mistral AI / EcoDataCenter

Borlänge, Sweden · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

CoreWeave / Applied Digital

Ellendale, North Dakota, US · 2027 (planned ready for service)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

15–22 months away

Undisclosed buyer / Applied Digital

Southern United States; state undisclosed · First half of 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

15–28 months away

CoreWeave / Local facility partners

Indonesia · three facilities · 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 20 announcements disclose no MW allocation. 3 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

40 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 8, 2026

Palantir

Nebius

Strategic partnership

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Preferred sovereign infrastructure partnership and planned integration for Palantir customers. No dedicated megawatt allocation or compute purchase value is disclosed. Excluded from investment and capacity totals.

Company announcementAssess this deal
Source ↗
Aug 11, 2026

Mistral AI

European enterprise coalition

Campus build

Undisclosed

Up to 1 GW

Program ambition · possible project overlap

Europe · sites not allocated

Program target: 2030

Build announced
Deal details

Program ambition for up to 1 GW by 2030, supported by enterprise compute commitments. Individual sites and incremental capacity beyond earlier Mistral projects are not allocated in this announcement. Excluded from physical capacity totals.

Company announcementRelated: Mistral AI / EcoDataCenter · 2026-02-11Assess this deal
Source ↗
Aug 4, 2026

CoreWeave

Local facility partners

Campus build

Undisclosed

360 MW

Contracted IT power · three facilities

Indonesia · three facilities

2028

15–28 months to target

Build announced
Deal details

Three Indonesian facilities with 360 MW of contracted IT power, expected online in 2028. This is the regional deployment allocation, not CoreWeave’s global contracted-power total.

Company announcementAssess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

Boyce, Louisiana, US

2027

3–16 months to target

Agreement signed
Deal details

Delta Forge 1: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 resultsAssess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

210 MW

Critical IT load

Southern United States; state undisclosed

First half of 2028

15–22 months to target

Agreement signed
Deal details

Delta Forge 2: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 resultsAssess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

United States; state not identified in cited release

2027

3–16 months to target

Agreement signed
Deal details

Polaris Forge 3: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 resultsAssess this deal
Source ↗
Jul 15, 2026

Crusoe

Lancium

Campus build

Undisclosed

1 GW

Planned campus capacity

Childress, Texas, US

No delivery date disclosed

Build announced
Deal details

Crusoe and Lancium announced a 1 GW campus for an unnamed hyperscale customer. Construction is expected to start in Q3 2026. This is a separate project from IREN’s Childress campus.

Crusoe announcementAssess this deal
Source ↗
Jul 6, 2026

Nscale

Nordkraft

Strategic partnership

Undisclosed

Undisclosed

Narvik, Norway

No delivery date disclosed

Agreement signed
Deal details

Joint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed.

Nscale July 6 announcementRelated: Microsoft / Nscale · 2026-04-14Assess this deal
Source ↗
Jun 24, 2026

CoreWeave

Conapto

Campus build

Undisclosed

Undisclosed

Stockholm, Sweden

Initial capacity online at announcement

In use at announcement
Deal details

Colocation agreement across two campuses. CoreWeave stated that initial capacity at Stockholm 4 South was already online. No deal-specific power allocation or contract value is disclosed. The company-wide active and contracted power figures are not assigned to these campuses.

CoreWeave investor announcementAssess this deal
Source ↗
May 6, 2026

Anthropic

SpaceX

Cloud compute

$1.25B/month

300+ MW

Colossus 1 compute

Location undisclosed

May 2026 (original target; later May–June ramp disclosed)

Target elapsed · confirm delivery

Agreement signed
Deal details

The May 6 announcement covers more than 300 MW at Colossus 1. SpaceX’s June 5 prospectus describes later agreements across Colossus 1 and 2: approximately 325,000 GPUs and $1.25B per month through May 2029, with reduced fees during the May–June ramp. Either party can terminate on 90 days’ notice after the initial three months. No guaranteed total or incremental MW is inferred. Orbital compute remains an expression of interest.

Hardware: 220,000+ NVIDIA GPUs

Anthropic, SpaceX compute dealSpaceX June 5, 2026 prospectus, section 4.3.4.5Assess this deal
Source ↗
Apr 20, 2026

Anthropic

Amazon Web Services

Cloud compute

$100B+ · 10 years

Up to 5 GW

Trainium and related compute

Location undisclosed

Nearly 1 GW by end of 2026

Agreement signed
Deal details

Anthropic committed more than $100B over ten years to AWS technologies for up to 5 GW of new Trainium and related capacity. Nearly 1 GW is expected before the end of 2026. Amazon also announced a $5B equity investment, with up to $20B more later; those equity figures are omitted from the dollar column.

Hardware: Trainium2–4

Anthropic, Amazon compute collaborationAssess this deal
Source ↗
Apr 14, 2026

Microsoft

Nscale

Cloud compute

Undisclosed

Undisclosed

Narvik, Norway

2027

3–16 months to target

Agreement signed
Deal details

Expanded Microsoft agreement adds more than 30,000 Rubin GPUs at Narvik in 2027. The 230 MW figure describes the campus, not the power allocated to this expansion.

Hardware: 30,000+ NVIDIA Rubin GPUs

Nscale announcementAssess this deal
Source ↗
Apr 10, 2026

Anthropic

CoreWeave

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

Later in 2026

0–4 months to target

Agreement signed
Deal details

Multi-year agreement to support Claude development and deployment, with capacity starting later in 2026. No exact dollar or megawatt figure is disclosed.

Company announcementAssess this deal
Source ↗
Apr 9, 2026

Meta

CoreWeave

Cloud compute

$21B · Approx. · through Dec 2032

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Expanded agreement for approximately $21B through December 2032. Includes new capacity and exercise of an option under a previous order. Read with the earlier agreement rather than treating both as independent projects.

CoreWeave announcementRelated: Meta / CoreWeave · 2025-09-30Assess this deal
Source ↗
Apr 6, 2026

Anthropic

Google / Broadcom

Cloud compute

Undisclosed

5 GW

TPU compute · May 6 disclosure

Primarily United States

2027

3–16 months to target

Agreement signed
Deal details

The April 6 announcement is for multiple gigawatts of next-generation TPU capacity starting in 2027. Anthropic’s May 6 recap states a 5 GW agreement with Google and Broadcom. No public dollar figure appears on either Anthropic page. Builds on a prior October 2025 TPU-capacity increase.

Hardware: Google TPUs

Anthropic, Google and Broadcom compute partnershipAnthropic, May 6 capacity updateAssess this deal
Source ↗
Apr 2, 2026

Nscale

Fortum

Campus build

Undisclosed

Undisclosed

Harjavalta, Finland

No delivery date disclosed

Build announced
Deal details

Site securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed.

Nscale announcementAssess this deal
Source ↗
Mar 27, 2026

Microsoft

Crusoe

Campus build

Undisclosed

900 MW

Planned campus capacity

Abilene, Texas, US

First building: mid-2027

3–16 months to target

Build announced
Deal details

New 900 MW campus serving Microsoft, next to the existing Abilene development. Includes two buildings and onsite generation. The combined 2.1 GW Abilene figure includes the existing campus.

Crusoe announcementAssess this deal
Source ↗
Mar 16, 2026

Meta

Nebius

Cloud compute

Up to $27B · 5 years

Undisclosed

Multiple locations · not named

Early 2027

3–16 months to target

Agreement signed
Deal details

Includes $12B of dedicated capacity and up to $15B of additional capacity that remains after sales to other customers. The $27B ceiling is not all dedicated capacity.

Hardware: NVIDIA Vera Rubin

Nebius announcementAssess this deal
Source ↗
Mar 16, 2026

Microsoft

Nscale

Cloud compute

Undisclosed

Up to 1.35 GW

Proposed compute capacity

Mason County, West Virginia, US

Late 2027

3–16 months to target

Letter of intent
Deal details

Letter of intent for up to 1.35 GW at Monarch. The campus’s potential power expansion above 8 GW is not the Microsoft allocation. A letter of intent is not a completed supply contract.

Hardware: NVIDIA Vera Rubin NVL72

Nscale announcementAssess this deal
Source ↗
Feb 27, 2026

OpenAI

Amazon Web Services

Cloud compute

$100B · 8 years · expansion

2 GW

Approximately · Trainium compute

Location undisclosed

Trainium4 expected in 2027

Agreement signed
Deal details

An additional $100B over eight years expands the earlier $38B AWS agreement. Approximately 2 GW of Trainium capacity is included. Amazon’s equity investment is separate.

Hardware: Trainium3 / Trainium4

OpenAI announcementAssess this deal
Source ↗
Feb 11, 2026

Mistral AI

EcoDataCenter

Campus build

€1.2B

Undisclosed

Borlänge, Sweden

2027

3–16 months to target

Build announced
Deal details

Long-term €1.2B infrastructure partnership at Borlänge. EcoDataCenter will build and operate the facility. The disclosed euro amount is retained without a dollar conversion.

Hardware: NVIDIA Vera Rubin

EcoDataCenter announcementAssess this deal
Source ↗
Jan 14, 2026

OpenAI

Cerebras

Cloud compute

Undisclosed

750 MW

Inference compute

Location undisclosed

Phased through 2028

Agreement signed
Deal details

OpenAI announced 750 MW of inference compute to be introduced in phases through 2028. The announcement does not disclose a contract price or individual sites.

Hardware: Cerebras wafer-scale systems

OpenAI announcementAssess this deal
Source ↗
Nov 20, 2025

Nscale

Verne

Campus build

Undisclosed

15 MW

Deployment power; IT versus facility basis not specified

Iceland

Deployment planned in 2026

0–4 months to target

Agreement signed
Deal details

15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal.

Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs

Nscale announcementAssess this deal
Source ↗
Nov 18, 2025

Anthropic

Microsoft Azure / NVIDIA

Cloud compute

$30B

Up to 1 GW

Additional compute capacity

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Anthropic committed to purchase $30B of Azure compute capacity and to contract additional capacity up to 1 GW, initially on NVIDIA Grace Blackwell and Vera Rubin systems. NVIDIA and Microsoft also committed to invest up to $10B and $5B in Anthropic; those equity figures are omitted from the dollar column. Amazon remains Anthropic’s stated primary cloud and training partner.

Hardware: Grace Blackwell / Vera Rubin

Anthropic, Microsoft and NVIDIA partnershipsAssess this deal
Source ↗
Nov 12, 2025

Anthropic

Fluidstack

Campus build

$50B

Undisclosed

Texas and New York, US

Sites coming online through 2026

Build announced
Deal details

Anthropic announced a $50B investment in U.S. computing infrastructure, building data centers with Fluidstack in Texas and New York. The announcement says Fluidstack can deliver gigawatts of power but does not state a megawatt figure. This is an infrastructure build, not a cloud offtake.

Anthropic, $50 billion American AI infrastructureAssess this deal
Source ↗
Nov 10, 2025

NVIDIA

CoreWeave

Cloud compute

$6.3B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

The results recap a $6.3B NVIDIA arrangement; the September 9 order gives NVIDIA access to residual unsold capacity. This backstop can overlap capacity sold to other customers and is excluded from aggregate purchase values. The date identifies the cited results disclosure.

CoreWeave third-quarter resultsCoreWeave registration filing: residual capacity termsAssess this deal
Source ↗
Nov 3, 2025

Microsoft

IREN

Cloud compute

$9.7B · Approx. · 5 years

200 MW

Critical IT load · Horizon 1–4

Childress, Texas, US

Phased through 2026

Agreement signed
Deal details

Approximately $9.7B over five years, with 20% prepayment. Horizon 1–4 support 200 MW of critical IT load within the 750 MW Childress campus; the full campus is not assigned to this contract.

Hardware: NVIDIA GB300

IREN announcementAssess this deal
Source ↗
Nov 3, 2025

Microsoft

Lambda

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Multibillion-dollar agreement for tens of thousands of NVIDIA GPUs. No exact contract price or megawatt allocation is disclosed in the announcement.

Hardware: NVIDIA GPUs, including GB300 NVL72

Lambda announcementAssess this deal
Source ↗
Oct 28, 2025

OpenAI

Microsoft Azure

Cloud compute

$250B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Microsoft disclosed an incremental $250B Azure services purchase by OpenAI. The equity ownership and prior investment are separate from this services commitment.

Microsoft quarterly filingAssess this deal
Source ↗
Sep 30, 2025

Meta

CoreWeave

Cloud compute

Up to $14.2B · Through Dec 2031

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Filed September 30 for a September 25 order. Up to approximately $14.2B through December 2031, subject to delivery and availability terms. An option to expand through 2032 is separate.

CoreWeave SEC filingRelated: Meta / CoreWeave · 2026-04-09Assess this deal
Source ↗
Sep 25, 2025

OpenAI

CoreWeave

Cloud compute

Up to $6.5B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

September expansion only. CoreWeave also disclosed a $4B May expansion and approximately $22.4B in cumulative OpenAI contracts. Do not add the cumulative figure again.

CoreWeave announcementRelated: OpenAI / CoreWeave · 2025-03-10Assess this deal
Source ↗
Sep 23, 2025

OpenAI

Oracle

Cloud compute

$300B+ · 5 years

Up to 4.5 GW

Planned compute capacity

United States · multiple sites

No delivery date disclosed

Agreement signed
Deal details

September disclosure of the July Oracle agreement: over $300B across five years and up to 4.5 GW of additional Stargate capacity. This is part of the Stargate program, not capacity additional to its headline total.

Oracle announcementRelated: OpenAI / Stargate (SoftBank, Oracle, MGX) · 2025-01-21Assess this deal
Source ↗
Sep 8, 2025

Microsoft

Nebius

Cloud compute

$17.4B · Approx. · through 2031

Undisclosed

Vineland, New Jersey, US

Late 2025 (announced target)

Target elapsed · confirm delivery

Agreement signed
Deal details

Approximately $17.4B for dedicated GPU capacity, subject to deployment and availability. Additional services could increase the value to approximately $19.4B. Microsoft can terminate delayed tranches under the filing’s conditions.

Nebius announcementNebius September 8 SEC filingAssess this deal
Source ↗
Aug 28, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

150 MW

Incremental critical IT load; Building 4

Ellendale, North Dakota, US

2027 (planned ready for service)

3–16 months to target

Agreement signed
Deal details

Third lease dated August 28 adds 150 MW to the initial 250 MW, bringing CoreWeave’s campus allocation to 400 MW. The record contains only the incremental allocation. Reported campus delivery remains attached to the original record to avoid counting it twice.

Applied Digital quarterly filingRelated: CoreWeave / Applied Digital · 2025-06-02Assess this deal
Source ↗
Aug 14, 2025

Fluidstack

TeraWulf

Campus build

Undisclosed

200+ MW

Critical IT load; approximately 250 MW gross facility capacity

Lake Mariner, New York, US

First approximately 40 MW targeted for first half of 2026

Target elapsed · confirm delivery

Agreement signed
Deal details

Two ten-year hosting agreements. Approximately $3.7B initial-term revenue; $8.7B includes optional extensions. Google’s $1.8B backstop and warrants are financing support, not another compute purchase. The possible 160 MW expansion is separate.

TeraWulf August 14 announcementAssess this deal
Source ↗
Jun 2, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

250 MW

Critical IT load under initial leases

Ellendale, North Dakota, US

First 100 MW targeted for Q4 2025

Delivery reported

Agreement signed
Deal details

Initial leases cover 250 MW for approximately 15 years, with approximately $7B expected revenue. A separate 150 MW option was subsequently exercised, taking the campus to 400 MW under contract. The initial allocation is not the whole campus. Hosting revenue is excluded from compute purchase totals.

Applied Digital June 2 filingApplied Digital fiscal Q4 2026 resultsAssess this deal
Source ↗
Mar 10, 2025

OpenAI

CoreWeave

Cloud compute

Up to $11.9B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Initial compute agreement. Later expansions are separate records; the September cumulative figure is not another contract.

CoreWeave announcementRelated: OpenAI / CoreWeave · 2025-09-25Assess this deal
Source ↗
Jan 21, 2025

OpenAI

Stargate (SoftBank, Oracle, MGX)

Campus build

$100B · $500B intended over four years

Undisclosed

United States · starts in Texas

Texas buildout underway at announcement

Build announced
Deal details

Stargate is a new company that intends to invest $500B over four years in U.S. AI infrastructure for OpenAI, beginning with $100B. Initial equity funders: SoftBank, OpenAI, Oracle, and MGX. Technology partners: Arm, Microsoft, NVIDIA, Oracle, and OpenAI. This is a project-company build, not a bilateral cloud offtake. The $100B figure is the initial deployment; the $500B figure is the stated intention.

OpenAI, Announcing The Stargate ProjectRelated: OpenAI / Oracle · 2025-09-23Assess this deal
Source ↗
Dec 23, 2024

xAI

NVIDIA

Campus build

Undisclosed

Undisclosed

Location undisclosed

In use by December 2024

In use at announcement
Deal details

xAI reported a 100,000-Hopper-GPU Colossus training system in use. The $6B funding round is not a compute contract price. This record describes a self-build milestone.

Hardware: 100,000 NVIDIA Hopper GPUs

xAI company updateAssess this deal
Source ↗
Dec 6, 2024

Cohere

Government of Canada

Campus build

Undisclosed

Undisclosed

Canada · site not named

No delivery date disclosed

Build announced
Deal details

Government announcement of support for a Canadian AI data center serving Cohere. The up-to-C$240M government contribution is not the total project cost or a compute purchase price. Builders are not named in this source.

Government of Canada announcementAssess this deal
Source ↗

From a delivery target to a power assessment

Use Time to Power to assess site readiness with grid, permitting, and project evidence. Workspace access is required.

Coverage and sources

Selected public compute agreements, infrastructure investments, and self-build milestones. Each record links to a company announcement or regulatory source. Dates and agreement status describe the cited announcement; delivery targets are not confirmation that capacity is available today.

Contract values, project budgets, and campus capacity can overlap. We do not add them into a market total. Missing figures remain undisclosed, and original currencies are retained. Financing rounds and government grants are not compute purchase prices.

Coverage is strongest in North America and Europe. Chinese labs and providers, private agreements, and smaller regional operators are not yet comprehensively covered. An absent company does not mean it has no deals.

Suggest a deal or correction