Research / Infrastructure
AI compute deals. When will the power arrive?
Who is buying capacity, who is building it, and when it is expected. Agreements and projects across AI labs, cloud providers, and neoclouds.
Dataset updated Sep 14, 2026 · Latest announcement Sep 8, 2026
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | 7.75 GW | 10.5 GW | 300 MW |
| IT power leases | 1.77 GW | — | 200 MW |
| Campus projects | 1.9 GW | — | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
Compute purchase agreements
$428.1B
Stated contract values, over their full terms
Additional upper-limit values
Up to $45.4B
Additional minimum values
Over $400B
11 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.
Compare buyers · 14 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| Palantir | 1 | — | — | — | 0 of 1 |
| Mistral AI | 2 | — | — | — | 1 of 2 |
| CoreWeave | 4 | — | — | — | 3 of 4 |
| Undisclosed buyer | 3 | — | — | — | 3 of 3 |
| Crusoe | 1 | — | — | — | 0 of 1 |
| Nscale | 3 | — | — | — | 1 of 3 |
| Anthropic | 6 | 5 GW | 6 GW | 300 MW | 3 of 6 |
| Microsoft | 6 | — | — | — | 4 of 6 |
| Meta | 3 | — | — | — | 1 of 3 |
| OpenAI | 7 | 2.75 GW | 4.5 GW | — | 0 of 7 |
| NVIDIA | 1 | — | — | — | 0 of 1 |
| Fluidstack | 1 | — | — | — | 1 of 1 |
| xAI | 1 | — | — | — | 0 of 1 |
| Cohere | 1 | — | — | — | 0 of 1 |
Time to Power
When is capacity expected?
17 dated targets · 23 without a first-capacity window
3 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
Reported delivery
Applied Digital / CoreWeave · 175 MW ready for service
Polaris Forge 1 campus; part of 400 MW contracted. Report date, not energization date.
2025
Original target passed
Vineland, New Jersey, US · Late 2025 (announced target)
First compute capacity · A first phase may cover only part of the agreement.
2025
Delivery reported
Ellendale, North Dakota, US · First 100 MW targeted for Q4 2025
First compute capacity · A first phase may cover only part of the agreement.
2026
Original target passed
Site not disclosed · May 2026 (original target; later May–June ramp disclosed)
First compute capacity · A first phase may cover only part of the agreement.
2026
Original target passed
Lake Mariner, New York, US · First approximately 40 MW targeted for first half of 2026
First compute capacity · A first phase may cover only part of the agreement.
2026
0–4 months away
Site not disclosed · Later in 2026
First compute capacity · A first phase may cover only part of the agreement.
2026
0–4 months away
Iceland · Deployment planned in 2026
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Boyce, Louisiana, US · 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
United States; state not identified in cited release · 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Narvik, Norway · 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Primarily United States · 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Abilene, Texas, US · First building: mid-2027
First power · A first phase may cover only part of the agreement.
2027
3–16 months away
Multiple locations · not named · Early 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Mason County, West Virginia, US · Late 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Borlänge, Sweden · 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
3–16 months away
Ellendale, North Dakota, US · 2027 (planned ready for service)
First compute capacity · A first phase may cover only part of the agreement.
2028
15–22 months away
Southern United States; state undisclosed · First half of 2028
First compute capacity · A first phase may cover only part of the agreement.
2028
15–28 months away
Indonesia · three facilities · 2028
First compute capacity · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 20 announcements disclose no MW allocation. 3 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
40 announcements
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Sep 8, 2026 | Palantir Nebius Strategic partnership | Undisclosed | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsPreferred sovereign infrastructure partnership and planned integration for Palantir customers. No dedicated megawatt allocation or compute purchase value is disclosed. Excluded from investment and capacity totals. Company announcement ↗Assess this deal |
| Aug 11, 2026 | Mistral AI European enterprise coalition Campus build | Undisclosed | Up to 1 GW Program ambition · possible project overlap | Europe · sites not allocated Program target: 2030 | Build announcedDeal detailsProgram ambition for up to 1 GW by 2030, supported by enterprise compute commitments. Individual sites and incremental capacity beyond earlier Mistral projects are not allocated in this announcement. Excluded from physical capacity totals. Company announcement ↗Related: Mistral AI / EcoDataCenter · 2026-02-11Assess this deal |
| Aug 4, 2026 | CoreWeave Local facility partners Campus build | Undisclosed | 360 MW Contracted IT power · three facilities | Indonesia · three facilities 2028 15–28 months to target | Build announcedDeal detailsThree Indonesian facilities with 360 MW of contracted IT power, expected online in 2028. This is the regional deployment allocation, not CoreWeave’s global contracted-power total. Company announcement ↗Assess this deal |
| Jul 27, 2026 | Undisclosed buyer Applied Digital Campus build | Undisclosed | 300 MW Critical IT load | Boyce, Louisiana, US 2027 3–16 months to target | Agreement signedDeal detailsDelta Forge 1: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values. Applied Digital July 27 results ↗Assess this deal |
| Jul 27, 2026 | Undisclosed buyer Applied Digital Campus build | Undisclosed | 210 MW Critical IT load | Southern United States; state undisclosed First half of 2028 15–22 months to target | Agreement signedDeal detailsDelta Forge 2: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values. Applied Digital July 27 results ↗Assess this deal |
| Jul 27, 2026 | Undisclosed buyer Applied Digital Campus build | Undisclosed | 300 MW Critical IT load | United States; state not identified in cited release 2027 3–16 months to target | Agreement signedDeal detailsPolaris Forge 3: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values. Applied Digital July 27 results ↗Assess this deal |
| Jul 15, 2026 | Crusoe Lancium Campus build | Undisclosed | 1 GW Planned campus capacity | Childress, Texas, US No delivery date disclosed | Build announcedDeal detailsCrusoe and Lancium announced a 1 GW campus for an unnamed hyperscale customer. Construction is expected to start in Q3 2026. This is a separate project from IREN’s Childress campus. Crusoe announcement ↗Assess this deal |
| Jul 6, 2026 | Nscale Nordkraft Strategic partnership | Undisclosed | Undisclosed | Narvik, Norway No delivery date disclosed | Agreement signedDeal detailsJoint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed. Nscale July 6 announcement ↗Related: Microsoft / Nscale · 2026-04-14Assess this deal |
| Jun 24, 2026 | CoreWeave Conapto Campus build | Undisclosed | Undisclosed | Stockholm, Sweden Initial capacity online at announcement | In use at announcementDeal detailsColocation agreement across two campuses. CoreWeave stated that initial capacity at Stockholm 4 South was already online. No deal-specific power allocation or contract value is disclosed. The company-wide active and contracted power figures are not assigned to these campuses. CoreWeave investor announcement ↗Assess this deal |
| May 6, 2026 | Anthropic SpaceX Cloud compute | $1.25B/month | 300+ MW Colossus 1 compute | Location undisclosed May 2026 (original target; later May–June ramp disclosed) Target elapsed · confirm delivery | Agreement signedDeal detailsThe May 6 announcement covers more than 300 MW at Colossus 1. SpaceX’s June 5 prospectus describes later agreements across Colossus 1 and 2: approximately 325,000 GPUs and $1.25B per month through May 2029, with reduced fees during the May–June ramp. Either party can terminate on 90 days’ notice after the initial three months. No guaranteed total or incremental MW is inferred. Orbital compute remains an expression of interest. Hardware: 220,000+ NVIDIA GPUs Anthropic, SpaceX compute deal ↗SpaceX June 5, 2026 prospectus, section 4.3.4.5 ↗Assess this deal |
| Apr 20, 2026 | Anthropic Amazon Web Services Cloud compute | $100B+ · 10 years | Up to 5 GW Trainium and related compute | Location undisclosed Nearly 1 GW by end of 2026 | Agreement signedDeal detailsAnthropic committed more than $100B over ten years to AWS technologies for up to 5 GW of new Trainium and related capacity. Nearly 1 GW is expected before the end of 2026. Amazon also announced a $5B equity investment, with up to $20B more later; those equity figures are omitted from the dollar column. Hardware: Trainium2–4 Anthropic, Amazon compute collaboration ↗Assess this deal |
| Apr 14, 2026 | Microsoft Nscale Cloud compute | Undisclosed | Undisclosed | Narvik, Norway 2027 3–16 months to target | Agreement signedDeal detailsExpanded Microsoft agreement adds more than 30,000 Rubin GPUs at Narvik in 2027. The 230 MW figure describes the campus, not the power allocated to this expansion. Hardware: 30,000+ NVIDIA Rubin GPUs Nscale announcement ↗Assess this deal |
| Apr 10, 2026 | Anthropic CoreWeave Cloud compute | Undisclosed | Undisclosed | Location undisclosed Later in 2026 0–4 months to target | Agreement signedDeal detailsMulti-year agreement to support Claude development and deployment, with capacity starting later in 2026. No exact dollar or megawatt figure is disclosed. Company announcement ↗Assess this deal |
| Apr 9, 2026 | Meta CoreWeave Cloud compute | $21B · Approx. · through Dec 2032 | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsExpanded agreement for approximately $21B through December 2032. Includes new capacity and exercise of an option under a previous order. Read with the earlier agreement rather than treating both as independent projects. CoreWeave announcement ↗Related: Meta / CoreWeave · 2025-09-30Assess this deal |
| Apr 6, 2026 | Anthropic Google / Broadcom Cloud compute | Undisclosed | 5 GW TPU compute · May 6 disclosure | Primarily United States 2027 3–16 months to target | Agreement signedDeal detailsThe April 6 announcement is for multiple gigawatts of next-generation TPU capacity starting in 2027. Anthropic’s May 6 recap states a 5 GW agreement with Google and Broadcom. No public dollar figure appears on either Anthropic page. Builds on a prior October 2025 TPU-capacity increase. Hardware: Google TPUs Anthropic, Google and Broadcom compute partnership ↗Anthropic, May 6 capacity update ↗Assess this deal |
| Apr 2, 2026 | Nscale Fortum Campus build | Undisclosed | Undisclosed | Harjavalta, Finland No delivery date disclosed | Build announcedDeal detailsSite securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed. Nscale announcement ↗Assess this deal |
| Mar 27, 2026 | Microsoft Crusoe Campus build | Undisclosed | 900 MW Planned campus capacity | Abilene, Texas, US First building: mid-2027 3–16 months to target | Build announcedDeal detailsNew 900 MW campus serving Microsoft, next to the existing Abilene development. Includes two buildings and onsite generation. The combined 2.1 GW Abilene figure includes the existing campus. Crusoe announcement ↗Assess this deal |
| Mar 16, 2026 | Meta Nebius Cloud compute | Up to $27B · 5 years | Undisclosed | Multiple locations · not named Early 2027 3–16 months to target | Agreement signedDeal detailsIncludes $12B of dedicated capacity and up to $15B of additional capacity that remains after sales to other customers. The $27B ceiling is not all dedicated capacity. Hardware: NVIDIA Vera Rubin Nebius announcement ↗Assess this deal |
| Mar 16, 2026 | Microsoft Nscale Cloud compute | Undisclosed | Up to 1.35 GW Proposed compute capacity | Mason County, West Virginia, US Late 2027 3–16 months to target | Letter of intentDeal detailsLetter of intent for up to 1.35 GW at Monarch. The campus’s potential power expansion above 8 GW is not the Microsoft allocation. A letter of intent is not a completed supply contract. Hardware: NVIDIA Vera Rubin NVL72 Nscale announcement ↗Assess this deal |
| Feb 27, 2026 | OpenAI Amazon Web Services Cloud compute | $100B · 8 years · expansion | 2 GW Approximately · Trainium compute | Location undisclosed Trainium4 expected in 2027 | Agreement signedDeal detailsAn additional $100B over eight years expands the earlier $38B AWS agreement. Approximately 2 GW of Trainium capacity is included. Amazon’s equity investment is separate. Hardware: Trainium3 / Trainium4 OpenAI announcement ↗Assess this deal |
| Feb 11, 2026 | Mistral AI EcoDataCenter Campus build | €1.2B | Undisclosed | Borlänge, Sweden 2027 3–16 months to target | Build announcedDeal detailsLong-term €1.2B infrastructure partnership at Borlänge. EcoDataCenter will build and operate the facility. The disclosed euro amount is retained without a dollar conversion. Hardware: NVIDIA Vera Rubin EcoDataCenter announcement ↗Assess this deal |
| Jan 14, 2026 | OpenAI Cerebras Cloud compute | Undisclosed | 750 MW Inference compute | Location undisclosed Phased through 2028 | Agreement signedDeal detailsOpenAI announced 750 MW of inference compute to be introduced in phases through 2028. The announcement does not disclose a contract price or individual sites. Hardware: Cerebras wafer-scale systems OpenAI announcement ↗Assess this deal |
| Nov 20, 2025 | Nscale Verne Campus build | Undisclosed | 15 MW Deployment power; IT versus facility basis not specified | Iceland Deployment planned in 2026 0–4 months to target | Agreement signedDeal details15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal. Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs Nscale announcement ↗Assess this deal |
| Nov 18, 2025 | Anthropic Microsoft Azure / NVIDIA Cloud compute | $30B | Up to 1 GW Additional compute capacity | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsAnthropic committed to purchase $30B of Azure compute capacity and to contract additional capacity up to 1 GW, initially on NVIDIA Grace Blackwell and Vera Rubin systems. NVIDIA and Microsoft also committed to invest up to $10B and $5B in Anthropic; those equity figures are omitted from the dollar column. Amazon remains Anthropic’s stated primary cloud and training partner. Hardware: Grace Blackwell / Vera Rubin Anthropic, Microsoft and NVIDIA partnerships ↗Assess this deal |
| Nov 12, 2025 | Anthropic Fluidstack Campus build | $50B | Undisclosed | Texas and New York, US Sites coming online through 2026 | Build announcedDeal detailsAnthropic announced a $50B investment in U.S. computing infrastructure, building data centers with Fluidstack in Texas and New York. The announcement says Fluidstack can deliver gigawatts of power but does not state a megawatt figure. This is an infrastructure build, not a cloud offtake. Anthropic, $50 billion American AI infrastructure ↗Assess this deal |
| Nov 10, 2025 | NVIDIA CoreWeave Cloud compute | $6.3B | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsThe results recap a $6.3B NVIDIA arrangement; the September 9 order gives NVIDIA access to residual unsold capacity. This backstop can overlap capacity sold to other customers and is excluded from aggregate purchase values. The date identifies the cited results disclosure. CoreWeave third-quarter results ↗CoreWeave registration filing: residual capacity terms ↗Assess this deal |
| Nov 3, 2025 | Microsoft IREN Cloud compute | $9.7B · Approx. · 5 years | 200 MW Critical IT load · Horizon 1–4 | Childress, Texas, US Phased through 2026 | Agreement signedDeal detailsApproximately $9.7B over five years, with 20% prepayment. Horizon 1–4 support 200 MW of critical IT load within the 750 MW Childress campus; the full campus is not assigned to this contract. Hardware: NVIDIA GB300 IREN announcement ↗Assess this deal |
| Nov 3, 2025 | Microsoft Lambda Cloud compute | Undisclosed | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsMultibillion-dollar agreement for tens of thousands of NVIDIA GPUs. No exact contract price or megawatt allocation is disclosed in the announcement. Hardware: NVIDIA GPUs, including GB300 NVL72 Lambda announcement ↗Assess this deal |
| Oct 28, 2025 | OpenAI Microsoft Azure Cloud compute | $250B | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsMicrosoft disclosed an incremental $250B Azure services purchase by OpenAI. The equity ownership and prior investment are separate from this services commitment. Microsoft quarterly filing ↗Assess this deal |
| Sep 30, 2025 | Meta CoreWeave Cloud compute | Up to $14.2B · Through Dec 2031 | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsFiled September 30 for a September 25 order. Up to approximately $14.2B through December 2031, subject to delivery and availability terms. An option to expand through 2032 is separate. CoreWeave SEC filing ↗Related: Meta / CoreWeave · 2026-04-09Assess this deal |
| Sep 25, 2025 | OpenAI CoreWeave Cloud compute | Up to $6.5B | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsSeptember expansion only. CoreWeave also disclosed a $4B May expansion and approximately $22.4B in cumulative OpenAI contracts. Do not add the cumulative figure again. CoreWeave announcement ↗Related: OpenAI / CoreWeave · 2025-03-10Assess this deal |
| Sep 23, 2025 | OpenAI Oracle Cloud compute | $300B+ · 5 years | Up to 4.5 GW Planned compute capacity | United States · multiple sites No delivery date disclosed | Agreement signedDeal detailsSeptember disclosure of the July Oracle agreement: over $300B across five years and up to 4.5 GW of additional Stargate capacity. This is part of the Stargate program, not capacity additional to its headline total. Oracle announcement ↗Related: OpenAI / Stargate (SoftBank, Oracle, MGX) · 2025-01-21Assess this deal |
| Sep 8, 2025 | Microsoft Nebius Cloud compute | $17.4B · Approx. · through 2031 | Undisclosed | Vineland, New Jersey, US Late 2025 (announced target) Target elapsed · confirm delivery | Agreement signedDeal detailsApproximately $17.4B for dedicated GPU capacity, subject to deployment and availability. Additional services could increase the value to approximately $19.4B. Microsoft can terminate delayed tranches under the filing’s conditions. Nebius announcement ↗Nebius September 8 SEC filing ↗Assess this deal |
| Aug 28, 2025 | CoreWeave Applied Digital Campus build | Undisclosed | 150 MW Incremental critical IT load; Building 4 | Ellendale, North Dakota, US 2027 (planned ready for service) 3–16 months to target | Agreement signedDeal detailsThird lease dated August 28 adds 150 MW to the initial 250 MW, bringing CoreWeave’s campus allocation to 400 MW. The record contains only the incremental allocation. Reported campus delivery remains attached to the original record to avoid counting it twice. Applied Digital quarterly filing ↗Related: CoreWeave / Applied Digital · 2025-06-02Assess this deal |
| Aug 14, 2025 | Fluidstack TeraWulf Campus build | Undisclosed | 200+ MW Critical IT load; approximately 250 MW gross facility capacity | Lake Mariner, New York, US First approximately 40 MW targeted for first half of 2026 Target elapsed · confirm delivery | Agreement signedDeal detailsTwo ten-year hosting agreements. Approximately $3.7B initial-term revenue; $8.7B includes optional extensions. Google’s $1.8B backstop and warrants are financing support, not another compute purchase. The possible 160 MW expansion is separate. TeraWulf August 14 announcement ↗Assess this deal |
| Jun 2, 2025 | CoreWeave Applied Digital Campus build | Undisclosed | 250 MW Critical IT load under initial leases | Ellendale, North Dakota, US First 100 MW targeted for Q4 2025 Delivery reported | Agreement signedDeal detailsInitial leases cover 250 MW for approximately 15 years, with approximately $7B expected revenue. A separate 150 MW option was subsequently exercised, taking the campus to 400 MW under contract. The initial allocation is not the whole campus. Hosting revenue is excluded from compute purchase totals. Applied Digital June 2 filing ↗Applied Digital fiscal Q4 2026 results ↗Assess this deal |
| Mar 10, 2025 | OpenAI CoreWeave Cloud compute | Up to $11.9B | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsInitial compute agreement. Later expansions are separate records; the September cumulative figure is not another contract. CoreWeave announcement ↗Related: OpenAI / CoreWeave · 2025-09-25Assess this deal |
| Jan 21, 2025 | OpenAI Stargate (SoftBank, Oracle, MGX) Campus build | $100B · $500B intended over four years | Undisclosed | United States · starts in Texas Texas buildout underway at announcement | Build announcedDeal detailsStargate is a new company that intends to invest $500B over four years in U.S. AI infrastructure for OpenAI, beginning with $100B. Initial equity funders: SoftBank, OpenAI, Oracle, and MGX. Technology partners: Arm, Microsoft, NVIDIA, Oracle, and OpenAI. This is a project-company build, not a bilateral cloud offtake. The $100B figure is the initial deployment; the $500B figure is the stated intention. OpenAI, Announcing The Stargate Project ↗Related: OpenAI / Oracle · 2025-09-23Assess this deal |
| Dec 23, 2024 | xAI NVIDIA Campus build | Undisclosed | Undisclosed | Location undisclosed In use by December 2024 | In use at announcementDeal detailsxAI reported a 100,000-Hopper-GPU Colossus training system in use. The $6B funding round is not a compute contract price. This record describes a self-build milestone. Hardware: 100,000 NVIDIA Hopper GPUs xAI company update ↗Assess this deal |
| Dec 6, 2024 | Cohere Government of Canada Campus build | Undisclosed | Undisclosed | Canada · site not named No delivery date disclosed | Build announcedDeal detailsGovernment announcement of support for a Canadian AI data center serving Cohere. The up-to-C$240M government contribution is not the total project cost or a compute purchase price. Builders are not named in this source. Government of Canada announcement ↗Assess this deal |
From a delivery target to a power assessment
Use Time to Power to assess site readiness with grid, permitting, and project evidence. Workspace access is required.
Coverage and sources
Selected public compute agreements, infrastructure investments, and self-build milestones. Each record links to a company announcement or regulatory source. Dates and agreement status describe the cited announcement; delivery targets are not confirmation that capacity is available today.
Contract values, project budgets, and campus capacity can overlap. We do not add them into a market total. Missing figures remain undisclosed, and original currencies are retained. Financing rounds and government grants are not compute purchase prices.
Coverage is strongest in North America and Europe. Chinese labs and providers, private agreements, and smaller regional operators are not yet comprehensively covered. An absent company does not mean it has no deals.
Suggest a deal or correction