All compute deals

CoreWeave compute deals

Public agreements, delivery targets, and source evidence for CoreWeave.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases
IT power leases760 MW
Campus projects

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

Stated contract values, over their full terms

Additional upper-limit values

Additional minimum values

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
CoreWeave43 of 4

Time to Power

When is capacity expected?

3 dated targets · 1 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

Applied Digital / CoreWeave · 175 MW ready for service

Polaris Forge 1 campus; part of 400 MW contracted. Report date, not energization date.

Company update · 2026-07-27

2025

Delivery reported

CoreWeave / Applied Digital

Ellendale, North Dakota, US · First 100 MW targeted for Q4 2025

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

CoreWeave / Applied Digital

Ellendale, North Dakota, US · 2027 (planned ready for service)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

15–28 months away

CoreWeave / Local facility partners

Indonesia · three facilities · 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

4 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Aug 4, 2026

CoreWeave

Local facility partners

Campus build

Undisclosed

360 MW

Contracted IT power · three facilities

Indonesia · three facilities

2028

15–28 months to target

Build announced
Deal details

Three Indonesian facilities with 360 MW of contracted IT power, expected online in 2028. This is the regional deployment allocation, not CoreWeave’s global contracted-power total.

Company announcementAssess this deal
Source ↗
Jun 24, 2026

CoreWeave

Conapto

Campus build

Undisclosed

Undisclosed

Stockholm, Sweden

Initial capacity online at announcement

In use at announcement
Deal details

Colocation agreement across two campuses. CoreWeave stated that initial capacity at Stockholm 4 South was already online. No deal-specific power allocation or contract value is disclosed. The company-wide active and contracted power figures are not assigned to these campuses.

CoreWeave investor announcementAssess this deal
Source ↗
Aug 28, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

150 MW

Incremental critical IT load; Building 4

Ellendale, North Dakota, US

2027 (planned ready for service)

3–16 months to target

Agreement signed
Deal details

Third lease dated August 28 adds 150 MW to the initial 250 MW, bringing CoreWeave’s campus allocation to 400 MW. The record contains only the incremental allocation. Reported campus delivery remains attached to the original record to avoid counting it twice.

Applied Digital quarterly filingRelated: CoreWeave / Applied Digital · 2025-06-02Assess this deal
Source ↗
Jun 2, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

250 MW

Critical IT load under initial leases

Ellendale, North Dakota, US

First 100 MW targeted for Q4 2025

Delivery reported

Agreement signed
Deal details

Initial leases cover 250 MW for approximately 15 years, with approximately $7B expected revenue. A separate 150 MW option was subsequently exercised, taking the campus to 400 MW under contract. The initial allocation is not the whole campus. Hosting revenue is excluded from compute purchase totals.

Applied Digital June 2 filingApplied Digital fiscal Q4 2026 resultsAssess this deal
Source ↗