Meta compute deals
Public agreements, delivery targets, and source evidence for Meta.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | — | — | — |
| Campus projects | — | — | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
Compute purchase agreements
$21B
Stated contract values, over their full terms
Additional upper-limit values
Up to $27B
Additional minimum values
—
2 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| Meta | 3 | — | — | — | 1 of 3 |
Time to Power
When is capacity expected?
1 dated targets · 2 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
2027
3–16 months away
Multiple locations · not named · Early 2027
First compute capacity · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 3 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
3 announcements
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Apr 9, 2026 | Meta CoreWeave Cloud compute | $21B · Approx. · through Dec 2032 | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsExpanded agreement for approximately $21B through December 2032. Includes new capacity and exercise of an option under a previous order. Read with the earlier agreement rather than treating both as independent projects. CoreWeave announcement ↗Related: Meta / CoreWeave · 2025-09-30Assess this deal |
| Mar 16, 2026 | Meta Nebius Cloud compute | Up to $27B · 5 years | Undisclosed | Multiple locations · not named Early 2027 3–16 months to target | Agreement signedDeal detailsIncludes $12B of dedicated capacity and up to $15B of additional capacity that remains after sales to other customers. The $27B ceiling is not all dedicated capacity. Hardware: NVIDIA Vera Rubin Nebius announcement ↗Assess this deal |
| Sep 30, 2025 | Meta CoreWeave Cloud compute | Up to $14.2B · Through Dec 2031 | Undisclosed | Location undisclosed No delivery date disclosed | Agreement signedDeal detailsFiled September 30 for a September 25 order. Up to approximately $14.2B through December 2031, subject to delivery and availability terms. An option to expand through 2032 is separate. CoreWeave SEC filing ↗Related: Meta / CoreWeave · 2026-04-09Assess this deal |