Palantir compute deals

Public agreements, delivery targets, and source evidence for Palantir.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases
IT power leases
Campus projects

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

Stated contract values, over their full terms

Additional upper-limit values

Additional minimum values

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Palantir10 of 1

Time to Power

When is capacity expected?

0 dated targets · 1 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

No dated first-capacity targets in this selection.

How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

1 announcement

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 8, 2026

Palantir

Nebius

Strategic partnership

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Preferred sovereign infrastructure partnership and planned integration for Palantir customers. No dedicated megawatt allocation or compute purchase value is disclosed. Excluded from investment and capacity totals.

Company announcementAssess this deal
Source ↗