All compute deals

Nscale compute deals

Public agreements, delivery targets, and source evidence for Nscale.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases
IT power leases
Campus projects

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

Stated contract values, over their full terms

Additional upper-limit values

Additional minimum values

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Nscale31 of 3

Time to Power

When is capacity expected?

1 dated targets · 2 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2026

0–4 months away

Nscale / Verne

Iceland · Deployment planned in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 2 announcements disclose no MW allocation. 1 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

3 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Jul 6, 2026

Nscale

Nordkraft

Strategic partnership

Undisclosed

Undisclosed

Narvik, Norway

No delivery date disclosed

Agreement signed
Deal details

Joint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed.

Nscale July 6 announcementAssess this deal
Source ↗
Apr 2, 2026

Nscale

Fortum

Campus build

Undisclosed

Undisclosed

Harjavalta, Finland

No delivery date disclosed

Build announced
Deal details

Site securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed.

Nscale announcementAssess this deal
Source ↗
Nov 20, 2025

Nscale

Verne

Campus build

Undisclosed

15 MW

Deployment power; IT versus facility basis not specified

Iceland

Deployment planned in 2026

0–4 months to target

Agreement signed
Deal details

15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal.

Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs

Nscale announcementAssess this deal
Source ↗