Yotta / Gorilla Technology
Announced 2026-04-30 · Undisclosed · Approx. $2.5B project value (July update)
Expansion separate from the earlier 5,120-GPU programme. April disclosure valued this project at approximately $2.8B; July 21 described Yotta 2 at approximately $2.5B without reconciling the difference. September 8 reports equipment deliveries across the wider Yotta programme, not operational acceptance of this tranche. Project value remains outside compute-purchase totals. No MW conversion is inferred from GPU count.
Delivery target: Original deployment completion target: September 30, 2026; first service date undisclosed
Yotta April 30 expansion announcement ↗Gorilla July 21 project value and location update ↗Gorilla September 8 equipment delivery update ↗
Assess the delivery assumptions
Check the site, power connection, permits, and delivery milestones behind this agreement with GreenCIO.